Ghana

Solar rural electrification is 30% cheaper than cost of grid expansion

Our rural folks continue to live in darkness despite the abundance of sunlight. 

According to the World Bank Data Sheet, one of the key issues in Africa’s Energy Sector is Low Access and Insufficient Capacity. Ghana as of 2012 has an electricity access rate of about 64.1%.  This means many folks in the rural segments are without electricity.  On rural electrification, the primary objective of the policy is to expand access as rapidly as can be afforded in a cost effective and environmentally friendly manner. The rural electrification policy includes a full menu of options which include on-grid and off-grid, mini grids, non-thermal and renewables.

It is important that strategies for rural electrification be renewable energy sources because Africa is extremely vulnerable to climate change and the continent has more solar radiation than any other continent on earth. 

Studies have revealed promising potential for this resource in Ghana. According to the SWERA Ghana Project report, Wa, the capital of the Upper West region, has the highest level of solar irradiation (5.524 KWh/m2-day) across the country. May is the month with the highest solar irradiation (5.897 KWh/m2-day), with August recording the lowest measurement (4.937kWh/m2-day) in Wa. Akim Oda on the contrary is the location that records the lowest radiation (4.567kWh/m2-day) measurements across the country. The highest measurement in Akim Oda was recorded in the month of April (5.176kWh/m2-day) and the lowest in August (3.802kWh/m2-day). This estimate tells that sunlight will provide useful solar energy for about 4 to 6 hours per day because during the early hours and late hours of the day the angle of the sun’s light is too low.

It is worth noting that only 2% of the total surface area of Ghana will give an average of 924 GigaWattHours of Solar Energy annually. 

In the tables below, let us examine closely the technical and financial potentials of a mini-grid Solar Power for a 250 household rural community which is about 18 to 20km to the National Power Grid extensions. The mini grid design is has a battery backup which is able to store power during the day which is consumed at night, the light is distributed using poles, these poles usually each carry a street light on it which pass through a village over a short distance then to household. In such areas, solar is not only a cost effective alternative for these communities, but also an effective method for improving health and quality of life in the developing world. 

For the unnamed community selected, the load demand per day for each household is 1.21kWh (Total Household Demand 302.5kWh/day) whiles the total demand for the Non-Household is 26.59kWh/Day.

Components

# of Pieces  Cost per Unit in USD

Tot Unit

Cost USD

Other Cost 10%  of Tot Total Cost in USD Life Span (Years)
300W Module 280 240 67,200

6,720

73,920 25
2V Cell @1500Ah 540 360 194,400

19,440

213,840

7-8 years

Table 1. SIZING AN SPV SYSTEM OF 80-100 KW CAPACITY WITH STORAGE – 250 HOUSEHOLDS

125kVA Inverter with CC     46,500 46,500

46,500

25

Peripherals *      

173,540

173,540

 
Total System Cost USD         $507,800  
Installation cost 15 to 20% of (a)         $101,560  
Estimated cost Low Voltage Distribution Network         $152,340  
Total Capital Cost of SPV SYSTEM (a+b+c) (CAPEX)        

$761,700

 
O&M System Cost **         $91,404  
Electrical Losses /year*** kWh         4434.75/yr  
Salvage Value **** USD         $50,780  
Total Energy Produced (kWh)     100*5.4*0.75*365*25 100*5.4*0.75*365*25 3,695,625  

* Cables, Poles, Joints, Installation Materials, Support and Storage Structures…etc

** O&M System Cost PV Mini-grid, and it’s generally 12% of CAPEX

*** Electrical losses is suggested generally to be 3% of total electricity generated.

**** Salvage value suggested to be 10% of total capital cost.

Assumptions

Interest on loan = 7%

Loan repayment period = 25years Equal payments of (principal + interest)

Battery life is 7 to 8 years. To be changed about 3 times in 25years

Table. 2

Financial Analysis of the Installed SPV System for the Community

O&M Cost $91,404
Battery replacement (2) $427,680
Initial CAPEX $761,700
Total Cost in 25years $1,280,784
Total Energy Produced in 25years 3,695,625 kWh 
Total Cost in 25 years

$1,280,784

LCOE

1280784/3695625

LCOE (Per kWh Cost in USD)

$ 0.347

PAYBACK PERIOD

761700/(147825*0.347)

761700/51295.27

PAYBACK PERIOD 14.8YEARS

Table. 3 CONSTRUCTION COST ESTIMATION OF MEDIUM VOLTAGE AND LOW VOLTAGE – NATIONAL GRID EXTENSION.

A community 18 – 20km from the Nearest Grid Station

Item Description  Cost/ Unit USD Tot Cost USD
1 33KV, 3phase Wood pole line complete with conductor, 10m poles 34,089/km 613,602
2 1phase consumer service connection complete with 7m service pole 772.2 7,722
3 1phase consumer service connection complete with energy meter 357.5 62,205
4 3phase consumer service connection complete with energy meter 690.3 22,090
5 50KVA, 3phase pole mounted transformer substation complete. (33KV) 15,406.3 46,219
6 1phase (2-wire) LV line with conductor complete with 9m pole  16,845/km 1685
7 1phase (3-wire) LV line conductor complete with 9m pole, pole  19,330/km 11590
8 3phase (4-wire) LV line complete with conductor, 9m pole, pole  21576/km 34500
  Total   799,613
  Construction Supervision cost (supervision and management of the construction phase) was estimated at 20%   159,923
  10% price contingency for price fluctuations. Furthermore a physical contingency of 10% was included in the total cost since the unit cost was based on conceptual design of the distribution system. Total 20%   159,923
  Engineering cost (detailed survey and design) was estimated at 10%   79961
  TOTAL COST FOR NATIONAL GRID EXTENSION   1,199,420

Source: National Electrification Scheme (NES) Master Plan Review (2011-2020) pg 49-52

** Average inflation is assumed to be 13% from 2011

Glaringly, it is evident that extending electricity to a rural community (250 household) of about 18 to 20km to the National Power Grid extensions through Solar Rural Electrification costing (CAPEX) $761,700 USD is less cheap than doing a National Grid Extension to the same community which costs $1,199,420 USD. A savings of about $400,000 USD (30% of the cost of National Grid Extension) can be made on such a project for a rural community. With a payback period of 14.8years and (LCOE) a per kWh charge of $0.347 USD, this project is Economically Viable International Standards.

The increasingly acknowledgement of renewable energy as the sustainable energy and the current tariff hikes in our thermal based electricity sector should be enough motivation for extensive Solar energy sources research in Ghana and Africa as a whole. 

Current efforts to mitigate DUMSOR, necessitates extensive renewable energy research and investment in Ghana. 

Providing reliable cost-effective power for rural villages is a long way to go, this will improve their standard of living for our future generation.

More attention should be given to Solar Energy, because Ghana has the Potential.

Author: Maxmillian Kwarteng

SPS-3SiL 

mkwarteng@3sil.com.gh 

odeneho21@hotmail.com 

0203369968

 

Show More

Henry Cobblah

Henry Cobblah is a Tech Developer, Entrepreneur, and a Journalist. With over 15 Years of experience in the digital media industry, he writes for over 7 media agencies and shows up for TV and Radio discussions on Technology, Sports and Startup Discussions.

Related Articles

Back to top button

Adblock Detected

ALLOW OUR ADS